We're building for the future!

This is your source for updates on eight capital projects that will transform our schools.

 

Centennial High School & Tommy Stewart Field 

$71.5 million • Field completed 2018 • School scheduled completion: 2021

Project Details

 

 

Central High School

$96.3 million • Scheduled completion: 2022

Project Details

 

 

Edison Middle School

$25.1 million • Scheduled completion: 2021

Project Details

 

 

Dr. Howard Elementary

$17.8 million • Scheduled completion: 2020

Project Details

 

 

International Prep Academy

$6 million • Scheduled completion: 2022

Project Details

 

 

South Side Elementary

$12.4 million • Scheduled completion: 2020

Project Details

 

McKinley Field

$6.9 million • Scheduled completion: 2020

Project Details

 
 

Spalding Park

$3.9 million • Completed: 2019

Project Details

 

 

See the timeline for all projects Ask a question or send feedback