Spalding Park: See the progress from Summer 2018

Construction at Spalding Park is well underway since the groundbreaking in May 2018. Site preparation and grading is ongoing for competition and practice fields, and the foundation for the concession building is complete. Mechanical and electrical work is ongoing, as well as the construction of dugouts.

This $3.8 million renovation in partnership with the Champaign Park District will provide updated athletic facilities to Central High School and Franklin Middle School.