Spalding Park

About the project

The Spalding Park project is a $3.6 million renovation in partnership with the Champaign Park District that will provide updated athletic facilities to Central High School and Franklin Middle School students, coaches and community.

What's happening now?

  • Spring 2018 - After meetings with athletics staff, the Champaign Park District, and a community info night (January 31), the project management team reviewed staff and community feedback on design plans and incorporated suggestions.

  • Summer 2018 - Construction began in late May. A formal groundbreaking event was held Thursday, May 31, 1:30 p.m., at Spalding Park, 900 N. Harris Avenue, Champaign. 

  • January 2019 - Project is scheduled to be complete and ribbon-cutting ceremony to be determined.

See the timeline for all projects

The Spalding Park improvements will allow us to provide:

  • New competition baseball field
    • Dugouts, bullpens, batting cages
    • Backstop/fencing/stadium netting
    • Field lighting, scoreboard, PA system
    • Bleachers
    • New practice infield
  • Support building
  • Basketball court with lighting
  • New competition tennis facility
    • 8 courts
    • Center aisle for access, spectators and officials
    • Court lighting

What will the changes look like?

The images below show a snapshot of the schematic designs as of May 31, 2018. See more in the schematic design PDF below. 

Download the PDF