Edison Middle School

About the project

The Edison Middle School project is a $25.8 million renovation that will bring much-needed upgrades to better serve our students and staff. The project will allow us to provide:

  • Exterior upgrades
  • Accessibility enclosures and upgrades
  • Health, Life Safety upgrades
  • Classroom renovations
  • Cafeteria and gymnasium replacement
  • HVAC system upgrades
  • Higher efficiency systems

What's happening now?

  •  Winter 2019 - The design phase will begin.
     
  •  Spring  2019 - Design will continue, and a community info night will be held on May 8, 5:30-7 p.m., to show schematic designs and a phasing plan and ask the community for feedback.
     
  • Summer 2019 - Design development phase ongoing.
     
  • Fall 2019 - Community information night held on Sept. 18 to review the design update and an updated phasing plan. Community feedback welcomed. Deisgn continues through fall.
     
  • Winter 2019-20 - Construction documents will be prepared with bidding in two phases in January and March.
     
  • Spring 2020 - Construction began in late May.
     
  • Summer 2020 - Demolition of existing gym and cafeteria.   Begin construction of new gym.  Renovation of third floor classrooms, and some second floor classrooms.  New power feed and switchgear serving the entire school. 

See the timeline for all projects

An update on all Unit 4 building projects was presented at Referendum Oversight Committee on March 2, 2020. Click HERE to view a PDF of the presentation.  

What will the changes look like?

The images below show the presentation from the Board of Education Meeting on Feb. 10, 2020.

Download the PDF

Below are selected slides from the Feb. 10, 2020 Board of Education presentation: