The Central High School project is moving along this fall. Community members can expect the following activity throughout the next four weeks:
 
  • Week of 9/24 - Continue backfill of demolished properties and site grading.
  • Week of 10/1 - Begin hazardous material abatement on more residential properties.  Begin site utilities for the future relocation of the temporary classroom trailers.
  • Week of 10/8 - Continue the above items.  
  • Week of 10/15 - Continue the above items.
  • Week of 10/22 - Begin hazardous material abatement on additional properties.
  • 10/30 - Community Info Night for Central, Centennial and McKinley Field at Central High School Library, 5:30 - 7 p.m.