Central High School: Construction activities for winter/spring 2019

The Central High School project is moving along. Community members can expect the following activity throughout the next several months:

  • Week of 12/17 (through early spring)
    • Residential demolition work (206 New, 615-629 W. Church)
    • YMCA building demolition (north half of the block)
  • Starting 1/4 (through early spring)
    • Park Avenue closes
    • Utility enabling work starts (sanitary and storm sewer work)
  • Starting 3/11 through 3/22 (during spring break)
    • Lynn Street closes for storm sewer work